Main points of wall panel installation

Update:05 Feb 2018
Summary:

1. Keep the wall clean Before installation should make […]

1. Keep the wall clean
Before installation should make metope clean, dry, smooth, highly elastic line leveling; in order to adapt to the local climate conditions, wainscoting opened the package, the best put in place for at least 48 hours to install.
2. Design the size beforehand
Before installation, we should first find each block and find it directly, then try it on once. After adjustment, it will be formally installed to avoid surface pattern confusion, uneven color, uneven corners, uneven size, uneven surface, black joints at joints and lax joints.
3. Wire inspection roof
Before operation, the top of the panel should be checked to check whether the top of the wall is straight. If there is a problem, correct it in time. To avoid the wainscoting cap thickness, rugged and split.
4. Wall face need to do moisture treatment
Because the wood products have a certain moisture content. If the wall is wet, it should be constructed after drying or moistureproof. For example, we should first make moistureproof layer on the wall, brush the waterproof and moistureproof coating, and keep the ventilation holes on the wall panels.
There is a gap on the surface of the 5. panel
The height difference of the surface of the clapboard should be less than 0.5mm, the width of the joint between the boards should be uniform, the size deviation should not be greater than 2mm, the length deviation of the diagonal length of the single panel is not greater than 2mm, and the perpendicularity deviation of the panel is not more than 2mm.
6. The angle of yin and Yang should be horizontal and vertical
It is the key and difficult point of construction to protect the wall of the wall. It should be paid special attention to. Must be the yin-yang angle of vertical and horizontal seam stitching, 45 degrees.
7. Kicking line and pressure bar must stick to the panel
The kickboard and the strip should be pressed close to the panel, and there should be no large gap. Fixed baseboard or strip nail spacing, generally not more than 300mm; the nail should be knocked into the flat, slab within the depth of 0.5~1.0mm, nailhole should use the same color oily and greasy.